Rattlesnake Elementary had an extremely short construction schedule. Over $2M worth of contracted work was completed in less than 3 months, with the remaining work completed while students were in class. Night shifts and weekend work were standard. Two additions were completed as well as mechanical upgrades and a general facelift throughout the entire existing building.
Missoula County Public Schools
Paradigm Architects
Spring 2017
│General Contractor
fadeIn
fadeIn
Rattlesnake Elementary had an extremely short construction schedule. Over $2M worth of contracted work was completed in less than 3 months, with the remaining work completed while students were in class. Night shifts and weekend work were standard. Two additions were completed as well as mechanical upgrades and a general facelift throughout the entire existing building.